Kapoor Tunnel

Kapoor Tunnel

The Kapoor Tunnel passes 1,000 ft (305 m) below two lakes.
Official name Kapoor Tunnel
Begins Sooke Lake Head Tank
48°30′34″N 123°41′29″W / 48.509520°N 123.691286°W / 48.509520; -123.691286
Ends Japan Gulch
48°27′39″N 123°34′23″W / 48.460766°N 123.573069°W / 48.460766; -123.573069
Maintained by Capital Regional District Integrated Water Services
Length 8.8 km (5.5 mi)
Conduit height 2.1 m (6 ft 11 in) max.
Conduit width 2.1 m (6 ft 11 in) max.
Capacity 580,000 m3/d (20,000,000 cu ft/d)
Construction began 1960
Opening date 1970

The Kapoor Tunnel is a straight 8.8 km (5.5 mi) subterranean route which is the main transport of water from the Sooke Lake to the Westshore, City of Victoria, Esquimalt, and the Saanich Peninsula. When it was determined that the Sooke Flowline would no longer meet the region's needs, the decision was made to excavate the tunnel. Prior to construction of the flowline, Arthur Adams, the consultant for the flowline construction, had proposed the Kapoor Tunnel be built. Unfortunately, that era's technology was not yet up to the task.[1]

Construction

The tunnel was formed by a miniature tunnel boring machine (TBM), which was built in Vancouver at a cost of $258,000. Excavation was undertaken from both ends with the intention of meeting in the middle. The machine was later abandoned and excavation was carried out manually due to the soft rock clogging the teeth and gears and causing motor burn outs. The contractor quit and the water district completed the task in 1967.[2] On completion, the tunnel was an engineering success. Even without modern laser technology, the tunnel was joined only 6 in (152 mm) off line.The project was almost incident free with the only major injury occurring when a worker's eye was damaged while drilling into a hole containing an undetonated stick of dynamite.

The project was a challenging feat due to a variety of factors:

Route

The tunnel runs from the head tank near Sooke Lake, which maintains a constant pressure to the Japan Gulch UV Plant near Goldstream Provincial Park.

Maintenance

This tunnel can convey 580 million litres/day, 10 times greater than the Sooke Flowline, and provides water to all municipalities, except Sooke and the Highlands. Its final cost was $5.6 million. The Sooke Flowline had been leaking and was vulnerable to blow downs and rock slides.

Every January, the tunnel is shut off and the city transfers over to the district's secondary Goldstream system. Workers walk the 8.8 km (5.5 mi) route to look for cracks and other defects.

References

  1. Hall, Del (1989). At The End of the Trail From Victoria. Victoria: Cougar Press Editions. ASIN B002IGIN76.
  2. Greater Victoria Water District (1991). History and General Information. Victoria: Greater Victoria Water District.
This article is issued from Wikipedia - version of the 9/28/2014. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.