Bakhtiari Dam

Bakhtiari Dam
Location of Bakhtiari Dam in Iran
Country Iran
Location Andimeshk County, Lorestan/Khuzestan Provinces
Coordinates 32°57′23.58″N 48°45′34.87″E / 32.9565500°N 48.7596861°E / 32.9565500; 48.7596861Coordinates: 32°57′23.58″N 48°45′34.87″E / 32.9565500°N 48.7596861°E / 32.9565500; 48.7596861
Status Under construction
Construction began 25 March 2013
Construction cost $2 billion USD
Dam and spillways
Type of dam Arch
Impounds Bakhtiari River
Height 325 m (1,066 ft)[1]
Length 434 m (1,424 ft)
Width (crest) 10 m (33 ft)
Width (base) 30 m (98 ft)
Dam volume 3,100,000 m3 (109,475,467 cu ft)
Spillway type Service, gate-controlled
Spillway capacity 5,830 m3/s (205,885 cu ft/s)
Reservoir
Creates Bakhtiari Reservoir
Total capacity 4,845,000,000 m3 (3,927,905 acre·ft)
Catchment area 6,288 km2 (2,428 sq mi)
Surface area 58.7 km2 (23 sq mi)
Power station
Hydraulic head 289 m (948 ft) (max.)
Turbines 6 x 250 MW Francis type
Installed capacity 1,500 MW
Annual generation 3 billion kWh (est.)
Website
http://en.iwpco.ir/Bakhtiari/default.aspx

The Bakhtiari Dam is an arch dam currently under construction on the Bakhtiari River within the Zagros Mountains on the border of Lorestan and Khuzestan Provinces, Iran. At a planned height of 325 metres (1,066 ft),[1] it will be the world's tallest dam once completed and withhold the second largest reservoir in Iran after the Karkheh reservoir. The main purpose of the dam is hydroelectric power production and it will support a 1,500 MW power station. By trapping sediment, the dam is also expected to extend the life of the Dez Dam 50 km (31 mi) downstream.

Background

Preliminary studies for the dam began in 1996 and were carried out by Mahab Qods Consulting Engineers. The studies were carried out over a period of 33 months and in March 2000, the results were given to Iran Water & Power Resources Development Co (IWPCO). In May 2005, IWPCO awarded consultation services for the project to Moshanir Consulting Engineers, Dezab Consulting Engineers, Econo-Electrowatt/Boyri and Stucky Pars Consulting Engineers.[1] On April 30, 2007 the construction contract was awarded to China's Sinohydro Corporation.[2] The contract is worth $2 billion and was to be funded with direct investment from China.[3][4] Sinohydro signed the 118-month contract on March 15, 2011 and was expected to be working with Iran's Farab.[5] But the Iranian government rejected Sinohydro's bid in late May 2012 and handed the project over to Khatam-al-Anbiya (KAA), which is controlled by the Iranian Revolutionary Guard Corps.[6] The KAA commander announced on 19 December 2012 that construction of the dam had begun with access roads leading to the project site.[7] On 25 March 2013, Iranian President Mahmood Ahmadinejad attended a groundbreaking ceremony for the dam, initiating its construction.[8]

Construction

During construction, a total of six bridges will be built to support workers, vehicles and equipment in addition to various access roads. To divert the river, two tunnels, 1,151 m (3,776 ft) and 1,180 m (3,871 ft) in length will be constructed at the dam's left abutment. They will have discharge capacities of 2,090 m3/s (73,808 cu ft/s) and 1,680 m3/s (59,329 cu ft/s) respectively. To divert the water, two roller-compacted concrete cofferdams will be constructed. The upstream cofferdam will be 51 m (167 ft) high and the downstream 25 m (82 ft). Material to construct the dam including aggregate will come from the actual excavation of the dam site along with three quarries in the area.[9]

Design

The Bakhtiari will be a 325 m (1,066 ft) tall and 434 m (1,424 ft) long variable-radius arch dam. It will be 10 m (33 ft) wide at its crest and 30 m (98 ft) wide at its base while being composed of 3,100,000 m3 (109,475,467 cu ft) of concrete. The dam's reservoir will have a normal capacity of 4,845,000,000 m3 (3,927,905 acre·ft) and an active or "useful" capacity of 3,070,000,000 m3 (2,488,890 acre·ft). At a normal elevation of 830 m (2,723 ft) above sea level, the reservoir will have a surface area of 58.7 km2 (23 sq mi), maximum width of 1 km (1 mi) and length of 59 km (37 mi). Its catchment area will be 6,288 km2 (2,428 sq mi).[9]

The dam will contain two spillways. The main service spillway will be an 11 m (36 ft) diameter tunnel in the right abutment with two flood gates. The discharge capacity of this spillway will be 5,830 m3/s (205,885 cu ft/s). The second spillway will be two radial gates on the dam's orifice with a discharge capacity of 1,510 m3/s (53,325 cu ft/s). The dam's powerhouse will be located underground at the left abutment. It will be 161 m (528 ft) long, 64 m (210 ft) high and 24 m (79 ft) wide; containing 6 x 250 MW vertical Francis turbine-generators. Before reaching the power station, water will be transferred by six 51 m (167 ft) long penstocks. Feeding water to the penstocks is a 504 m (1,654 ft) long headrace tunnel with a three gate intake structure.[9]

See also

References

  1. 1 2 3 "Bakhtiari Project Information". IWPCO. Retrieved 30 January 2011.
  2. "New Awarded Projects". FARAB Co. Retrieved 30 January 2011.
  3. "Iran News Roundup October 6, 2010". Iran Tracker. Retrieved 30 January 2011.
  4. "China dams overseas" Check |url= value (help). Probe International. Retrieved 30 January 2011.
  5. "SINOHYDRO Signed the Contract to Build Iran's Bakhtiary Project". Sinohydro Corportation. 15 Mar 2011. Retrieved 8 May 2011.
  6. "Iranian contractor to build world's tallest arch dam, Chinese bid rejected". Tehran Times. Retrieved 30 May 2012.
  7. "Iran starts building second-tallest dam". Gant Daily. 20 December 2012. Archived from the original on 28 December 2012. Retrieved 3 March 2013.
  8. "News: Bakhtiari, World 's Highest Dam, Kicks off in the Presence of Mahmood Ahmadinejad". Iran Water and Power Resources Development Co. 13 April 2013. Retrieved 6 May 2013.
  9. 1 2 3 "Bakhtiari Technical Specifications". IWPCO. Retrieved 30 January 2011.