Bagger 288 (Excavator 288), built by the German company Krupp for the energy and mining firm Rheinbraun, is a bucket-wheel excavator or mobile strip mining machine.

The Bagger 288 bucket-wheel excavator

When its construction was completed in 1978, Bagger 288 superseded Big Muskie as the heaviest land vehicle in the world, at 13,500 tons.[1] In 1995, it was itself superseded by the slightly heavier Bagger 293 (14,200 tons). NASA's Crawler-Transporter still remains the largest self-powered land vehicle in the world, since bucket-wheel excavators are powered by an external power source, and the Overburden Conveyor Bridge F60s hold the title of largest land vehicle of any type by physical dimensions.

Objective

The Bagger 288 was built for the job of removing overburden before coal mining at the Hambach stripmine in Germany. It can excavate 240,000 tons of coal or 23,240,000 cubic metres of overburden daily[2] the equivalent of a football field (soccer) dug to 30 m (98 ft) deep. The coal produced in one day fills 2400 coal wagons. The excavator is up to 220 m (721 ft) long (slightly shorter than Baggers 287 and 293) and approximately 96 m (315 ft) high. The Bagger's operation requires 16.56 megawatts of externally supplied electricity.[3] It can travel 2 to 10 m (6.6 to 32.8 ft) per minute (0.1 to 0.6 km/h). The chassis of the main section is 46 m (151 ft) wide and sits on 3 rows of 4 caterpillar track assemblies, each 3.8 m (12 ft) wide. The large surface area of the tracks means the ground pressure of the Bagger 288 is very small (1.71 bar or 24.8 psi); this allows the excavator to travel over gravel, earth and even grass without leaving a significant track. It has a minimum turning radius of approximately 100 metres, and can climb a maximum gradient of 1:18 (5° incline).

The excavating head itself is 21.6 m (70 ft 10 in) in diameter and has 18 buckets each holding 6.6 cubic metres (8.6 cu yd) of overburden.

By February 2001, the excavator had completely exposed the coal source at the Tagebau Hambach mine and was no longer needed there. In three weeks it made a 22-kilometre (14 mi) trip to the Tagebau Garzweiler, traveling across Autobahn 61, the river Erft, a railroad line, and several roads. The move cost nearly 15 million German marks and required a team of seventy workers. Rivers were crossed by placing large steel pipes for the water to flow through and providing a smooth surface over the pipes with rocks and gravel. Special grass was seeded to smooth its passage over valuable terrain. Moving Bagger 288 in one piece was more economical than disassembling the excavator and moving it piece by piece.

The Bagger 288 is one of a group of similar sized and built vehicles, such as Bagger 281 (built in 1958), Bagger 285 (1975), Bagger 287 (1976), Bagger 293 (1995), etc.[3]

288 and related excavators at the Garzweiler stripmine

In popular culture

See also

Notes

External links

Coordinates: 51°03′54″N 6°30′28″E / 51.065°N 6.5078°E / 51.065; 6.5078

This article is issued from Wikipedia - version of the 12/1/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.